Site Establishment

Start Date
17 June 2025

Comments
Complete sign in and walk through
Established water and  power availability

Date completed
17 June 2025

Cleaning

Start date
17 – 20 June 2025



Date completed
95% Completed awaiting removal of bee removal

Before Cleaning Gallery
After Cleaning Gallery

Repairs

Start date
23 – 25 June 2025



Comments
Repairs complete apart from the area of the bees

Date completed
24 June 2025

 

Before Repairs Gallery
After Repairs Gallery

Sealing of roof

Start Date

24-25 June 2025
26 – 30 June 2025

01 – 03 July 2025

Comments

Hand painting of of sealer
1st Coat
2nd Coat

Date completed

26 June 2025

Before Sealing Gallery
After Sealing Gallery
Risk and Incidents

Bee Hive on roof (see layout)

Risk / Incident
18 June 2025
Bee Hive on roof (see layout)
30 June 2025


11 July 2025

14 July 2025

Comments
Log with hospital to remove the bee hive for us to proceed.
Spoke to Lichen from Ward 1
They have appointed a bee keeper to come and remove in July
Bees removed 
Roof sealed

Person to Action 

Marlan Naicker

Seelan Naicker to follow-up

Bees Removed 11 July 2025
roof sealed 14 July 2025

Risk / Incident
23 June 2025
Plumbing pipe leaking on the roof

Comments

Seelan to address with FMU (Sibongile) 

Person to Action 

Seelan Naicker

Risk / Incident
28 June 2025
Plumbing pipe repaired by us and roof repairs done

Comments

Pipe sealed

Person to Action 

Seelan Naicker completed 28 June 2025

Other findings

Start Date

 

Comments

 

Date completed