Kitchen and Linen
Site Establishment
- Access Points to working areas
- Access to Power
- Access to Water
Start date
17 June 2025
Â
Comments
Complete sign in and walk through
Established water and power availability
Date completed
17 June 2025
Cleaning
- Sweeping and Cleaning
- Power wash roof
Start date
24 – 29 June 2025
Comments
Cleaning – Open Spaces
Date completed
Removal of tree growth
- Trees growing on roof
- Due to Water tank leaks
Start date
25Â June 2025
Comments
Removal of vegetation growth
Water tank leak ACTION NEEDED
Date completed
26 June 2025
Repairs
- Check, repair cracks, tears and breaks of torchon
Start date
03-07 July 2025
Comments
Date completed
1st Solar panel testing
- Audit and record solar panel output before cleaning and sealing
Start date
07 July 2025
Comments
Access to container granted by Cynthia
471 v
62.8A
33.7kw
Date completed
07 July 2025
Solar panel cleaning
- Washing of panels
Start date
03 July 2025
Comments
Cabled Tidied up with cable ties so we can pressure wash the surface
Date completed
2nd Solar panel testing
- Audit and record solar panel output after cleaning and sealing
Start date
10 July 2025
Comments
Date completed
Sealing of roof
- 1st coat of sealer to be sprayed on
- 2nd coat of sealer to be sprayed on
- Hand painting of sealer in difficult to reach areas
Start date
07 July 2025
Comments
Access to container granted by Cynthia
264 v
70.2 A
35.3 kw
Date completed
10 July 2025
Risk and Incidents
Water tank has a severe leak.
The tank does not have a lid to close the water input, this is a health risk.
These have to be repaired in order to prevent the growth of vegetation on the roof.
The leaks also have to be stopped for us to have a dry surface for repairs and sealing on the roof.
Below is a gallery of the poor condition of the water storage tanks