Site Establishment
- Access Points to working areas
- Access to Power
- Access to Water
Start date
22 October 2025
Comments
Date completed
22 October 2025
Cleaning
- Sweeping and Cleaning
- Power wash roof
Start date
22 October 2025
Comments
Date completed
22 October 2025
Repairs
- Check, repair cracks, tears and breaks of torchon
Start date
23 October 2025
Comments
Date completed
Sealing of roof
- 1st coat of sealer to be sprayed on
- 2nd coat of sealer to be sprayed on
- Hand painting of sealer in difficult to reach areas
Start date
03/11/2025
Comments
Date completed
04/11/2025
Other findings
The downpipe was blocked and the water dammed up on the roof. The water then went into the holes in these two pipe and leaked into ward 8
These holes have been sealed to prevent this from happening again and further to this the downpipes were cleaned out by the hospital maintenance team